The client was concerned that its supply chain would be unable to keep up with ambitious growth targets and would hinder its ability to achieve identified goals.
Accenture undertook a 10-month global supply chain transformation exercise. The project team had eight full-time members from Accenture, with inputs from two overseas subject-matter experts and a client team of 12 full-time members. The two phases of the exercise were the diagnosis phase and the implementation phase:
Diagnosis phase (4 months):
Implementation phase (6 months):